  • UGC NET MBA Unit – 8 Statistics & Operations Management PYQ

    1. Which of the following is a measure of central tendency?

    A. Range
    B. Variance
    C. Median
    D. Standard deviation

    Correct Answer: C


    2. The difference between the highest and lowest value in a dataset is called:

    A. Mean deviation
    B. Standard deviation
    C. Range
    D. Coefficient of variation

    Correct Answer: C


    3. Which probability distribution describes the number of events occurring in a fixed interval of time or space?

    A. Normal distribution
    B. Poisson distribution
    C. Student’s t distribution
    D. Binomial distribution

    Correct Answer: B


    4. When population variance is unknown and sample size is small (<30), hypothesis testing uses:

    A. z–test
    B. t–test
    C. chi-square test
    D. F–test

    Correct Answer: B


    5. The coefficient of correlation ranges between:

    A. 0 to +1
    B. –1 to +1
    C. 0 to +10
    D. –10 to +10

    Correct Answer: B


    6. PERT analysis uses which type of time estimation?

    A. Most likely time
    B. Probabilistic time estimates
    C. Deterministic time estimates
    D. Linear time estimates

    Correct Answer: B


    7. EOQ (Economic Order Quantity) model attempts to:

    A. Minimise labour time
    B. Minimise fluctuation in demand
    C. Minimise total ordering and carrying costs
    D. Maximise storage capacity

    Correct Answer: C


    8. Which layout is suitable when product variety is high and production volume is low?

    A. Process layout
    B. Product layout
    C. Fixed position layout
    D. Cellular layout

    Correct Answer: A


    9. A chart showing order and completion time for jobs to be scheduled is:

    A. Activity chart
    B. Control chart
    C. Gantt chart
    D. Pareto chart

    Correct Answer: C


    10. Quality that is measured by statistical techniques is known as:

    A. TQM
    B. Quality function deployment
    C. Statistical quality control
    D. Lean quality control

    Correct Answer: C


    11. Six Sigma aims at limiting defects to:

    A. 3.4 defects per million opportunities
    B. 300 defects per million
    C. 34 defects per thousand
    D. Zero defects

    Correct Answer: A


    12. Which of the following is not a component of TQM philosophy?

    A. Continuous improvement
    B. Employee involvement
    C. Customer focus
    D. Increasing production speed

    Correct Answer: D


    13. ERP stands for:

    A. Enterprise Realistic Planning
    B. Enterprise Resource Planning
    C. Enterprise Resource Programming
    D. Enterprise Result Planning

    Correct Answer: B


    14. In queuing theory, the waiting line characteristics include:

    A. Arrival pattern, Service pattern, Queue discipline
    B. Production capacity, Layout design, Customer value
    C. Demand level, Price, Marginal utility
    D. Forecast accuracy and Break–even cost

    Correct Answer: A


    15. In transportation problems, the number of basic feasible solutions should be equal to:

    A. m + n – 1
    B. m × n
    C. m + n
    D. m – n

    (where m = origin, n = destination)